veeam replication job failover and failback

  • February 27, 2026
  • 4 comments
  • 20 views

we have initiated veeam replication job from pr site to dr site and failover to dr site,at dr site after failover we imported vm to VCD and renamed vm to new one and makes changes to replica on VCD,after this we failback to production and commit failback,but changes done on dr site vm are not showing up on pr site vm, what could be the possible issues.  

4 comments

Chris.Childerhose
Forum|alt.badge.img+21
  • Veeam Legend, Veeam Vanguard
  • February 27, 2026

If I was to guess it is the import to VCD that is causing the issue as there are other changes being done that Veeam may not track.  I have not done this so I could be way off but this is only an assumption.

Not sure if the documentation helps here - https://helpcenter.veeam.com/docs/vbr/userguide/failover_failback.html?ver=13

 


  • Author
  • Comes here often
  • February 27, 2026

VCD uses the same vm from vcenter,so changes made to vcd vm should reflect on replica vm on dr site?


coolsport00
Forum|alt.badge.img+21
  • Veeam Legend
  • February 27, 2026

Hi ​@rajasohaib - probably best to check in with Veeam Support to see what could be causing this issue. Could be expected behavior; could be a bug. Curious what they find out.


Chris.Childerhose
Forum|alt.badge.img+21
  • Veeam Legend, Veeam Vanguard
  • February 27, 2026

VCD uses the same vm from vcenter,so changes made to vcd vm should reflect on replica vm on dr site?