Question April 25 2024

  • 25 April 2024
  • 1 comment
  • 16 views

Userlevel 7
Badge +22

A stress management company called “Burke’s Stressed out Sys Admins” has two locations in the city of Moncton. They are leveraging backup copy jobs in order to follow the 3 2 1 rule since they have a backup repository in the second location. 

They recently expanded to Toronto and have acquired a small data center there. They have also decided to turn their second location in Moncton into a full blown production location and want to lower RTO to under 10 minutes.  “Stressed Out"’s backup administrator Nutty Ned would like to start leveraging Veeam CDP. Where would it be best to place the Backup Server? Hint:

As I side note Nutty Ned wants to move to Toronto to enjoy the glamours nightlife. 


1 comment

Userlevel 7
Badge +20

The backup server should go in whatever happens to be the target site.  If that is the second Moncton site then there or if Toronto will be the target site then it should be placed there.  As the saying goes - “It depends”.  😋

Comment