hello,

i have two Vmware Clusters now both in 6.7 version i want to upgrade to 7 version but for some hardware reaseans i can’t upgrade replication cluster. i already have a replication job in veaam replicate VMs from the master cluster to the replication cluster, my question is if i upgrade the master cluster to 7 version is the replication will work ???? 

Best answer by MicoolPaul

Morning :)

 

The VMs don’t care which version they’re on, so Veeam won’t care either, the key thing is to not upgrade the virtual machine hardware version above what is supported for 6.7.

 

The full table is here and depending on your 6.7 version this means not going above version 14 or 15

https://kb.vmware.com/s/article/1003746

12 comments

MicoolPaul
Forum|alt.badge.img+23
  • Answer
  • September 22, 2022

Morning :)

 

The VMs don’t care which version they’re on, so Veeam won’t care either, the key thing is to not upgrade the virtual machine hardware version above what is supported for 6.7.

 

The full table is here and depending on your 6.7 version this means not going above version 14 or 15

https://kb.vmware.com/s/article/1003746


  • Author
  • New Here
  • September 22, 2022

good Morning,

thank you Mr Paul  


MicoolPaul
Forum|alt.badge.img+23
  • September 22, 2022

good Morning,

thank you Mr Paul  

One final thing, just make sure your version of Veeam is patched to a new enough version to support vSphere 7.0

 

The full list of minimum versions for vSphere support is located here:

https://www.veeam.com/kb2443


Stabz
Forum|alt.badge.img+8
  • Veeam Legend
  • September 22, 2022

Hello
Just in complement if you are upgrading your Vmware to 7u3 be sure that your Veeam is in the latest version too (11a).

 

https://www.veeam.com/kb2443


  • Author
  • New Here
  • September 22, 2022

hello,

yes exactly veaam version is 10 i’am thinking to update to 11 is that need a change in licensing ?


Stabz
Forum|alt.badge.img+8
  • Veeam Legend
  • September 22, 2022

hello,

yes exactly veaam version is 10 i’am thinking to update to 11 is that need a change in licensing ?

No need, the licence file still the same :)


  • Author
  • New Here
  • September 22, 2022

hello, 

ok great thank you.


Scott
Forum|alt.badge.img+9
  • Veeam Legend
  • September 22, 2022

I’d also advise looking at VMware compatibility lists to make sure everything else is going to work too. 

Are you using linked vCenters or 2 totally separate unlinked DataCenters? 

6.7 is on borrowed time so best get a plan to upgrade :)


dloseke
Forum|alt.badge.img+8
  • Veeam Vanguard
  • September 22, 2022

Speaking from experience, this will be fine, but as noted, make sure your VM’s on the 7.0 cluster don’t get their virtual hardware upgraded beyond the versions compatible with the 6.7 cluster.


victorwu
Forum|alt.badge.img+7
  • Veeam Vanguard
  • September 22, 2022

The master and replication clusters are managed by same vCenter Server ?


Forum|alt.badge.img+1

Hi All,

I have a question about completing replication jobs if the replication windows exceeds. 

 

For the initial replication, Veeam will transfer the base full size of the replicated VM. Let's suppose it's a huge size VM and initial replication did not finish in the repli action window.

When the next schedule run, will Veeam start transferring from the beginning for the initial full or incremental replica that does not finish, or it will continue from the stopped point abd replication does not take another time and size?

 

I have read about (resume disconnect) but need to make sure from the experts? 

https://helpcenter.veeam.com/docs/backup/vsphere/replica_resume_disconnect.html?ver=110

Let's suppose the replication window from(17:00-23:30) only.

 

Thanks 


HunterLAFR
Forum|alt.badge.img+8
  • Veeam Legend
  • January 14, 2023

Hi All,

I have a question about completing replication jobs if the replication windows exceeds. 

 

For the initial replication, Veeam will transfer the base full size of the replicated VM. Let's suppose it's a huge size VM and initial replication did not finish in the repli action window.

When the next schedule run, will Veeam start transferring from the beginning for the initial full or incremental replica that does not finish, or it will continue from the stopped point abd replication does not take another time and size?

 

I have read about (resume disconnect) but need to make sure from the experts? 

https://helpcenter.veeam.com/docs/backup/vsphere/replica_resume_disconnect.html?ver=110

Let's suppose the replication window from(17:00-23:30) only.

 

Thanks