The environment described in this architecture is one main datacenter with 500 Nutanix AHV VMs with 100TB of source data. All local backups will be targeted to Hardened Repositories grouped in a Scale-out Backup Repository. Offsite backups will also target Veeam Hardened Repositories. VMs will require 2vCPUs, 4GB of RAM, and 200GB of disk space.

4 comments

jsb00227
Forum|alt.badge.img+3
  • Comes here often
  • 13 comments
  • July 5, 2024

Thanks @vmJoe - just to say also, really appreciate these blueprint documents!  This really helped me map the typical vSphere Veeam components over to the AHV variants/naming.  


vmJoe
Forum|alt.badge.img+8
  • Author
  • Veeam MVP
  • 67 comments
  • July 5, 2024

@jsb00227 I am glad I could help!


waqasali
Forum|alt.badge.img+3
  • Influencer
  • 196 comments
  • November 6, 2024

I face an issue in the Nutanix environment in AHV Veeam creates a snapshot of VMs for backup purposes those snapshots are kept in place till the next backup job runs for CBT reference purposes. On the next run new snapshot is created and the old one is used for CBT data collection and then the old snapshot is deleted after a successful backup.